Friday, March 21, 2008

FOUNTAIN REPORT - discussion on 20.3.2008

firstly, we all went through the design and finalized it. the waterfall looks as it is in bulla's prev post...
we then discussed on the positives and negatives abt the design...
damroo n i will be going to the zoo asap n collect info abt the solutions to the monkey problem..
2 way n moddey will go to the construction site to find out the construction cost (of the structure above the pathway)
hawaa is supposed to gather info abt the lighting...all the stuff nada talked off
patel will find abt the acoustic repellant (soln to monkey problem) n more abt the tap n material to be used
nada has to calculate the water input available, output required n ways to increase the water output....
dats it 4 now........
next meeting on sunday...9 pm...our usual time...

cheers
capacity...